October 16, 2024
The majority of the new underground infrastructure work is now complete! This includes extensive electrical and networking conduit throughout the foundation and site, as well as sewer lines, plumbing, waterlines for a new fire suppression system, and irrigation.
Grading around the site is nearly complete, and paving of the new parking lot will begin by the end of the month.
Delays in the delivery of structural steel—critical columns and custom fasteners—have slowed the progress of the roof assembly. However, the contractors have been extremely flexible and have adjusted their schedules to prefabricate and prepare as many sections of the building on-site as possible. When the steel arrives, the new gable roof line will come together quickly, thanks to the extensive work completed in advance.